Current capital projects

Home > Our community > Planning & projects > Current capital projects

We're working to create vibrant urban centres, a balanced transportation network and an inclusive community. Infrastructure projects improve and maintain outdoor spaces, buildings, active transportation networks, utilities, roads and bridges. 

Est. cost: $350,000
Est. start: Summer 2024
Est. end: Fall 2024

The Burtch Sanitary Trunk is a critical element of the City’s wastewater infrastructure and is currently in need of immediate repair due to hydrogen sulfide degradation...

Est. cost: $7 million
Est. start: April 2024
Est. end: June 2024

Install a total of 1,300m of 1200 diameter transmission mainline along Burtch Rd (at Byrns Rd) to the existing 1200mm trunk main stubbed off at Raymer Ave and Gordon Dr...

Est. cost: $10.7 Million
Est. start: Spring 2025
Est. end: Winter 2025

The asphalt pathway within Guisachan Heritage Park will be completed.

 

Est. cost: $30,000
Est. start: Spring 2024
Est. end: Spring 2024

Upgrades to existing Cassiar Lift Station on Rifle Rd, including new pumps, internal components, and standby power.

Est. start: Summer 2025
Est. end: Fall 2025

Extension of sanitary sewer mains and services to properties still on septic systems.  Work on the west side of Rutland Road started in 2023 and will be completed spring...

Est. cost: $19.5 Million
Est. start: 2022
Est. end: 2026

Work includes foreshore improvements at the northern extent of Hot Sands beach with replacement of sand with a cobble and planting zone to control erosion in this zone ...

Est. cost: $575,000
Est. start: Fall, 2024
Est. end: Winter, 2024

Project includes concrete barrier curb & gutter (both sides), 1.8m concrete sidewalk (north side) boulevard with street trees and driveway crossings.
 

...
Est. cost: $350,000
Est. start: Fall 2024
Est. end: Spring 2025

The objective of this project is to provide upgrades to the existing sanitary and water infrastructure networks as the existing systems are due for renewal. 

Est. cost: $2.5 million
Est. start: Summer 2024
Est. end: Fall 2024

Project consists of the replacement of existing internal piping and components at the Daon Pump Station.  Upgrades will allow for future reservoir expansion and system...

Est. start: Fall 2024
Est. end: Fall 2024