Burtch Sanitary Trunk Upgrade
The Burtch Sanitary Trunk is a critical element of the City’s wastewater infrastructure and is currently in need of immediate repair due to hydrogen sulfide degradation within the existing concrete pipe. In order to upgrade the trunk, the City has opted to do so via a Cured-In-Place-Pipe (CIPP) lining program as the desired means of rehabilitation. Benefits of utilizing this trenchless technology include its modest cost compared to a traditional excavate and replace method, accelerated timeline to project completion as well as significantly reduced public disruption.
Tentative schedule of work tasks:
- April 8 to 10 - Directional drill of north-end bypass pipe under Spall/Clement intersection. COMPLETE.
- April 22 to 27 - North end bypass mobilization and temporary Rail Trail ramp setup. Rail Trail ramps will be setup adjacent Hardy Street and Vineland Street. COMPLETE
- April 29 to May 17 - Lining of sewer trunk north of Hwy 97.
- Hardy Street (April 29 and April 30) COMPLETE
- Enterprise Way (May 1 and May 2) COMPLETE
- Enterprise Court (May 5) COMPLETE
- Parkinson Way (May 6) COMPLETE
- Parkinson Recreation Centre (May 7 to May 9) COMPLETE
- North side of Hwy 97 west of pedestrian overpass (May 12) COMPLETE
- Hwy 97 crossing to Sutherland Ave (May 13) COMPLETE
- North end of Sutherland Ave (May 14) COMPLETE
- Cleanup (May 15 to May 17) COMPLETE
- May 6 to 17 - Setup of temporary, shallow bury bypass sleeves along Burtch Rd under Sutherland Ave, Dickson Ave, Springfield Rd and to the laneway just south of Sutherland Ave, east side of Burtch Rd. COMPLETE
- May 13 to 21 - Setup of temporary road ramps over the bypass pipe at driveways for 1985 Burtch Rd, 1995 Burtch Rd, 2125 Burtch Rd (south driveway only), 2175 Burtch Rd, the northbound lanes of Burtch Rd adjacent Mill Creek as well as Byrns Rd just east of the roundabout. A temporary, shallow bury bypass sleeve for access to 2225 Burtch Rd is also planned. COMPLETE
- May 21 to 25 - Bypass mobilization and setup on Burtch Rd south of Hwy 97. COMPLETE
- May 29 to June 8 - Lining of sewer trunk south of Hwy 97.
- Sutherland Ave east of Burtch Rd (May 29) COMPLETE
- Burtch Rd, Sutherland Ave to Dickson Ave (May 30) COMPLETE
- Burtch Rd, Dickson Ave to Springfield Rd (May 31 and June 1) COMPLETE
- Burtch Rd, Springfield Rd to Byrns roundabout (June 4 to June 7) COMPLETE
- Temporary overland bypass pipe removal (June 9 to June 14) COMPLETE
- June 12 to June 22 - Removal of all temporary ramps and shallow bury access points and reinstatement of existing roadways. General rehabilitation of site and demobilization. COMPLETE