Road report
Road information is based on issued road usage permits. All public and private contractors are required to obtain a road usage permit for work affecting traffic flow. Click on a coloured line on the map for details about traffic impacts.
Permit number: RUP2025-0005
MAYER RD to SPRINGFIELD RD
January 14, 2025 - 9:00am to January 14, 2026 - 3:00pm
Lane Drop - Multi Lane Road
Abbott St 3061 - shallow utility installation. Road will be closed 7am to 5pm Mon to Fri.
Permit number: RUP2024-0795
ABBOTT ST to PANDOSY ST
August 27, 2024 (All day) to February 28, 2025 (All day)
Full Road Closure, No Through Traffic, Detour
MEIKLE AVE to NEWSOM AVE
August 27, 2024 (All day) to February 28, 2025 (All day)
Full Road Closure, No Through Traffic, Detour
Annual Permit 2025 - no excavation. Various City of Kelowna streets
Permit number: RUP2025-0067
LAKESHORE PL to BARNABY RD
February 3, 2025 - 9:30am to February 7, 2025 - 3:00pm
Single Lane Alternating
SPRINGFIELD RD to HICKORY RD
January 30, 2025 -
9:00am to 3:00pm
Single Lane Alternating
VINE PL to HILLTOWN DR
February 3, 2025 -
9:00am to 3:00pm
Single Lane Alternating
Barnard Ave 328 - Installing hanger bards on Facia Signs for CIBC.
Permit number: RUP2025-0079
Project contact: Patrick Martin
WATER ST to PANDOSY ST
January 29, 2025 - 8:00am to January 30, 2025 - 7:00pm
No Disruption
Belaire 1840 & Chandler St 1850 - hoarding sidewalk for office site, garbagte disposal, storage C-Can, loading and unloading of trucks. Site is fully fenced.
Permit number: RUP2025-0035
DEVONSHIRE AVE to CHANDLER ST
January 1, 2025 (All day) to March 31, 2025 (All day)
No Disruption
PRIDHAM AVE to BELAIRE AVE
January 1, 2025 (All day) to March 31, 2025 (All day)
No Disruption
Bertram Ave 1333 - garbage bin in 2 City parking stalls
Permit number: RUP2024-0944
FULLER AVE to CAWSTON AVE
October 8, 2024 (All day) to January 31, 2025 (All day)
No Disruption
Bertram St (Leon to Harvey Ave ) NB & SB - construction of the north ramp overpass. Works include asphalt, landscaping, concrete removal, deep and shallow foundation work, construction of an ongrade and suspended concrete ramp structure.
Permit number: RUP2024-0141
HARVEY AVE to LEON AVE
March 4, 2024 - 7:00am to April 1, 2025 - 5:00pm
Full Road Closure, No Through Traffic, Detour
Bertram St 1333 - opening up a section of sidewalk bet corner of Bertrams St and & Cawsons Ave and site entrance to 1333 Bertram. Install Fortis conduit and an 832. Restoring sidewalk once completed.
Permit number: RUP2025-0069
BERTRAM ST to RICHTER ST
January 21, 2025 - 7:00am to March 14, 2025 - 5:00pm
No Disruption
FULLER AVE to CAWSTON AVE
January 21, 2025 - 7:00am to March 14, 2025 - 5:00pm
No Disruption
Bertram St 1333 - lay down area for construction material
Permit number: RUP2025-0043
BERTRAM ST to LANE
January 2, 2025 (All day) to January 31, 2025 (All day)
Full Road Closure, No Through Traffic, Detour
Boynton Pl 630 - BA 100m2 parks parking lot is currently prohibiting construction equipment access to the North side of our construction site. Construction access will be required for a number of months in order to accommodate the equipment needed to ins
Permit number: RUP2024-0828
HIGHPOINTE DR to CARAMILLO RD
September 1, 2024 (All day) to March 31, 2025 (All day)
No Disruption
Boynton Pl 630 - parking space and sidewalk use for construction in area.
Permit number: RUP2025-0061
HIGHPOINTE DR to CARAMILLO RD
January 1, 2025 (All day) to June 30, 2025 (All day)
No Disruption
Cadder Ave 768 - tree removal. Roadside allows adequate space for lift truck access but does not leave enough room for a safe drop zone. Lane closure required so debris can be staged and safely chipped
Permit number: RUP2025-0063
RICHTER ST to SPRINGFIELD RD
January 27, 2025 -
9:00am to 2:00pm
Single Lane Alternating
Chandler St/Belaire Ave/Pridham - use of street and sidewalk for site office, garage disposal storage. C-can loading and unloading of trucks. Site is fully fenced.
Permit number: RUP2024-1148
DEVONSHIRE AVE to CHANDLER ST
January 1, 2025 (All day) to March 31, 2025 (All day)
No Disruption
DEVONSHIRE AVE to CHANDLER ST
January 1, 2025 (All day) to March 31, 2025 (All day)
No Disruption
PRIDHAM AVE to BELAIRE AVE
January 1, 2025 (All day) to March 31, 2025 (All day)
No Disruption
Clement Ave 647 - Sidewalk closure along Clement Ave. to allow for excavation of building which requires existing sidewalk removal, backfill ,and re-in statement of sidewalk to city standards. Existing sidewalk is 60m x 1.2 = 79m2. Please refer to attache
Permit number: RUP2025-0041
Project contact: Fraser Campbell
Email: [email protected]
ST PAUL ST to RICHTER ST
January 11, 2025 (All day) to June 30, 2025 (All day)
No Disruption
Clement Ave 647 - Working for Fortis BC to replace four power poles in the alley at 647 Clement, we will be digging in the new poles on Jan 23rd and 24th, the remainder of the time on site will be working in the air on the power lines.
Permit number: RUP2025-0065
Project contact: Darren Belanger
Email: [email protected]
ST. PAUL ST to LANE
January 23, 2025 - 8:00am to January 30, 2025 - 2:30pm
Lane Drop - Multi Lane Road, No Disruption
Comment:Abbott St 3061/Cedar Ave - extend construction fencing to the edge of the roadway to allow for a safer work area for site personnel as well as the general public. Ongoing construction of an 87 unit wood frame, 7 story building.
The developer did
Permit number: RUP2023-0972
ABBOTT ST to PANDOSY ST
January 1, 2024 - 7:00am to August 31, 2025 - 7:00pm
No Disruption
MEIKLE AVE to NEWSOM AVE
January 1, 2024 - 7:00am to August 31, 2025 - 7:00pm
No Disruption
Demobilization of 70ft Crawler crane and man lift from excavation with 270 mobile crane.
Current closure is for 3 days, however, expectation is to expedite demobilization and shrink closure duration if possible.
Permit number: RUP2025-0060
ST PAUL ST to BERTRAM ST
January 20, 2025 - 8:00am to January 22, 2025 - 4:30pm
Full Road Closure, No Through Traffic, Detour
Dougal Rd S 165 - sidewalk closure for building construction purposes. Sidewalk closure signs posted and pedestrians detoured to sidewalk on other side of the street. 60 meters used. TMP attached
Permit number: RUP2024-1014
GRAY RD to VALLEYVIEW RD
October 31, 2024 (All day) to April 9, 2025 (All day)
No Disruption
Dougall Rd N 540 - Install Telus, Fortis and Shaw behind curb/ sidewalk. No impact to foot or road traffic.
Leathhead between Froelich and Dougall
Dougall between Leathead and McIntosh
Permit number: RUP2025-0057
MCINTOSH RD to LEATHEAD RD
January 20, 2025 - 7:00am to January 24, 2025 - 5:00pm
No Disruption
TARTAN RD to DOUGALL RD N
January 20, 2025 - 7:00am to January 24, 2025 - 5:00pm
No Disruption
Doyle Ave 550 / St Paul St- Jersey barrier set up along alley, Doyle Ave and St Paul for public safety from construction traffic and future excavation
Permit number: RUP2023-0973
Project contact: Lauren Cooper
Email: [email protected]
DOYLE AVE to CAWSTON AVE
January 1, 2024 (All day) to December 31, 2025 (All day)
Lane Drop - Multi Lane Road
ST PAUL ST to BERTRAM ST
January 1, 2024 (All day) to December 31, 2025 (All day)
Lane Drop - Multi Lane Road
DOYLE AVE to CAWSTON AVE
January 1, 2024 (All day) to December 31, 2025 (All day)
Lane Drop - Multi Lane Road
Eso Crt 4253 - dig and repair in the Utility right-of-way to repair Rogers conduit. The dig and repair location is beside the PED located beside the walkway bet 4245 and 4249 Eso Crt.
Permit number: RUP2025-0053
WEST END OF ROAD to TORRS RD
January 28, 2025 - 9:00am to January 29, 2025 - 4:00pm
No Disruption
Frost Rd / chute Lake Cres/Treadgold Crt - Continued from permit 2024-1103 which was closed. Connect Frost Rd from Treadgold to Chute Lake Rd and add round-a-bout at the intersection of Chute Lake Rd, Frost Rd & Chute Lake Cres
Permit number: RUP2025-0040
TREADGOLD CT to KILLDEER RD
January 9, 2025 - 7:00am to April 15, 2025 - 9:00pm
Single Lane Alternating
CHUTE LAKE CR to FROST RD
January 9, 2025 - 7:00am to April 15, 2025 - 9:00pm
Single Lane Alternating
Frost Rd 1003-1111 - emergency Fortis duct repair in grass boulevard on the north east corner of Frost @ Gordon Dr
Permit number: RUP2024-1114
Project contact: Brad Hanks
Email: [email protected]
GORDON DR to STEELE RD
December 5, 2024 - 7:00am to January 24, 2025 - 5:00pm
No Disruption
Frost Rd 1055 - the project involves constructing a secure pedestrian scaffold tunnel along the sidewalk at the frontage of road.
Permit number: RUP2024-1052
Project contact: Josh Arneson
Email: [email protected]
GORDON DR to STEELE RD
December 2, 2024 - 7:00am to December 31, 2025 - 6:00pm
No Disruption
Gaggin Rd/Gertsmar Rd - pole access and manhole access for cable placing and splicing. No excavation for this work. Working on existing infrastructure.
Permit number: RUP2025-0048
Project contact: Todd Basso
Email: [email protected]
GAGGIN RD to MORGAN RD
January 23, 2025 - 9:00am to January 24, 2025 - 3:30pm
Single Lane Alternating
TAYLOR RD to GERSTMAR RD
January 23, 2025 - 9:00am to January 24, 2025 - 3:30pm
Single Lane Alternating
Hoarding - portion of road.
Permit number: RUP2024-1000
GORDON DR to ASPEN CT
November 1, 2024 - 7:00am to February 6, 2025 - 5:00pm
Single Lane Alternating
KLO & Spiers (KLO Bridge and Round-a-bout Project) - install Telus Conduit as part of Telus infrastructure. Fortis is already there and will be using their flaggers.
Permit number: RUP2025-0056
Project contact: Bob McWilliams
Email: [email protected]
LEADER RD to SPIERS RD
January 27, 2025 - 9:00am to February 7, 2025 - 3:30pm
Single Lane Alternating
LEADER RD to SPIERS RD
January 27, 2025 (All day) to February 7, 2025 (All day)
LEADER RD to SPIERS RD
January 27, 2025 (All day) to February 7, 2025 (All day)
SPIERS RD to HALL RD
January 27, 2025 (All day) to February 7, 2025 (All day)
SPIERS RD to HALL RD
January 27, 2025 (All day) to February 7, 2025 (All day)
SPIERS RD to HALL RD
January 27, 2025 - 9:00am to February 7, 2025 - 3:30pm
Single Lane Alternating
PARSONS RD to KLO RD
January 27, 2025 (All day) to February 7, 2025 (All day)
PARSONS RD to KLO RD
January 27, 2025 (All day) to February 7, 2025 (All day)
PARSONS RD to KLO RD
January 27, 2025 - 9:00am to February 7, 2025 - 3:30pm
Single Lane Alternating
KLO Bridge Upgrade, Re-locate 3PH Primary Overhead Primary Overhead Line - COK Project. Relocating the OH powerline to the south side of KLIO Rd to accommodate the new bridge construction. Will be installing 9 poles, 16 anchors and removing 6 poles and 5
Permit number: RUP2024-1077
SPIERS RD to HALL RD
December 3, 2024 - 9:00am to February 3, 2025 - 3:00pm
Single Lane Alternating
LEADER RD to SPIERS RD
December 3, 2024 - 9:00am to February 3, 2025 - 3:00pm
Single Lane Alternating
Kuipers Cres 808 - seacan on City road shoulder for moving unloading purposes.
Permit number: RUP2025-0038
Email: [email protected]
HEWETSON AVE to DOUGHERTY AVE
January 17, 2025 (All day) to January 23, 2025 (All day)
No Disruption
Lakeshore Rd 3377 - deliveries, concrete pours etc for this project.
Permit number: RUP2025-0052
Project contact: Dean Jones
Email: [email protected]
RICHTER ST to LANFRANCO RD
January 10, 2025 - 7:00am to March 15, 2025 - 4:00pm
No Disruption
Lark St 5145 - catch basin repair
Permit number: RUP2025-0076
CURLEW DR to CURLEW CT
January 20, 2025 - 10:30am to January 24, 2025 - 3:00pm
No Disruption
Lawrence Ave 375 #305 - We are doing some installation near roof edge and were advised by city staff to get a sidewalk use permit so that we can place caution signage and tape below the area of work. Install antenna equipment and cables near the roof edg
Permit number: RUP2025-0068
WATER ST to PANDOSY ST
January 18, 2025 - 8:00am to February 28, 2025 - 5:00pm
No Disruption
LEON AVE to LAWRENCE AVE
January 18, 2025 - 8:00am to February 28, 2025 - 5:00pm
No Disruption
Leckie Pl - Telus shallow utility installation works along Leckie Pl frontage from Just west of Dilworth Dr to Okanagan Rail Trail. TCP to assist cyclists/pedestrians along Rail Trail/Leckie ATC corridor passing active work zone.
Permit number: RUP2025-0073
WEST END OF ROAD to DILWORTH DR
January 20, 2025 - 7:00am to February 21, 2025 - 5:30pm
No Disruption
Leon Ave 278 non excavation work only. Deliveries and entering or exiting site.
Permit number: RUP2025-0022
Project contact: Stephanie Mattson
Email: [email protected]
ABBOTT ST to WATER ST
January 1, 2025 - 7:00am to December 31, 2025 - 5:00pm
Lane Drop - Multi Lane Road
Noble Crt 1550 - construction trailer on City road shoulder and block sidewalk along west side of Noble Crt. (two way traffic to be maintained) Pedestrians can cross Noble Crt on Bernard Ave and use sidewalk on the East side of Noble Crt
Permit number: RUP2024-0695
Project contact: Joe Reynolds
Email: [email protected]
SOUTH END OF ROAD to BERNARD AVE
July 25, 2024 (All day) to June 30, 2025 (All day)
No Disruption
Parks Mtce Duties - non excavation. Tree trimming, irrigation etc.
Permit number: RUP2025-0020
WATER ST to PANDOSY ST
January 15, 2025 - 8:00am to January 15, 2026 - 2:30pm
Lane Drop - Multi Lane Road, Single Lane Alternating
CROWLEY AVE to ETHEL ST
January 20, 2025 - 9:00am to January 24, 2025 - 2:30pm
Single Lane Alternating
ETHEL ST to GORDON DR
January 20, 2025 - 9:00am to January 24, 2025 - 2:30pm
Single Lane Alternating
BELGO RD to GARNER RD
January 20, 2025 - 9:00am to January 24, 2025 - 2:30pm
Lane Drop - Multi Lane Road, Single Lane Alternating
BEGBIE RD to JOHN HINDLE DR
January 20, 2025 - 9:00am to January 24, 2025 - 2:30pm
Lane Drop - Multi Lane Road, Single Lane Alternating
JOHN HINDLE DR to MCKINLEY RD
January 20, 2025 - 9:00am to January 24, 2025 - 2:30pm
Lane Drop - Multi Lane Road, Single Lane Alternating
JOE RICHE RD to BLACK MOUNTAIN DR
January 22, 2025 - 9:00am to January 24, 2025 - 2:30pm
Lane Drop - Multi Lane Road
FROST RD to BARNABY RD
January 22, 2025 - 9:00am to January 24, 2025 - 2:30pm
Lane Drop - Multi Lane Road
MCKENZIE RD to TREETOP RD
January 22, 2025 - 9:00am to January 24, 2025 - 2:30pm
Lane Drop - Multi Lane Road
Pridham Ave 1380 - construction deliveries
Permit number: RUP2025-0036
Project contact: Mike Partington
Email: [email protected]
DEVONSHIRE AVE to CHANDLER ST
January 13, 2025 - 7:00am to December 31, 2025 - 3:00pm
Single Lane Alternating
Pridham Ave 1380 - crane dismantling. Will need Belaire Ave at Chandler St closed to all traffic.
Permit number: RUP2025-0049
Project contact: Mike Partington
Email: [email protected]
DEVONSHIRE AVE to CHANDLER ST
January 24, 2025 - 7:00am to January 27, 2025 - 4:00pm
Full Road Closure, No Through Traffic, Detour
DEVONSHIRE AVE to CHANDLER ST
January 24, 2025 - 7:00am to January 27, 2025 - 4:00pm
Full Road Closure, No Through Traffic, Detour
Reconfiguration of the gas main on site. When we were performing valve maintenance in November, a leg of the existing gas main had to be disconnected to allow for that work to be completed. This project aims to reestablish this leg of gas main, with the n
Permit number: RUP2025-0071
Phone: 250-868-4518
Email: [email protected]
COMMERCIAL DR to NORTH END OF ROAD
January 20, 2025 - 7:00am to January 31, 2025 - 4:00pm
No Disruption
Richter St 1875 - use back lane for storage and receiving deliveries on an ongoing basis for construction. Expanding space in back lane from existing permit already in place. New permit issued for expanding area. Both will expire Dec 31, 2024 then can com
Permit number: RUP2025-0047
Project contact: Sarb Hayer
Email: [email protected]
DEAD END to ROWCLIFFE AVE
January 1, 2025 (All day) to January 31, 2025 (All day)
Lane Drop - Multi Lane Road
Richter St 2609 - site hoarding area for storage of materials (Bike lane not affected. Total area is 55 m2 in area.
Permit number: RUP2024-0065
KINNEAR AVE to WARDLAW AVE
January 15, 2024 (All day) to March 31, 2025 (All day)
No Disruption
Richter St 2609-2611 - flush and camera STM Line
Permit number: RUP2025-0058
KINNEAR AVE to WARDLAW AVE
January 1, 1900 (All day) to December 31, 2025 (All day)
Richter St 2609-2611 - flush and camera STM line
Permit number: RUP2025-0059
KINNEAR AVE to WARDLAW AVE
January 14, 2025 - 9:00am to January 31, 2025 - 2:00pm
Single Lane Alternating
Royal Ave & Long St - laydown and trailer site/seacan placement.
Permit number: RUP2023-0990
Project contact: Brady Allen
Email: [email protected]
LONG ST to PANDOSY ST
January 1, 2024 - 7:00am to April 30, 2025 - 5:30pm
Lane Drop - Multi Lane Road
Royal Ave 416 (Lane) - lane closed from Long St to the east property of 416 Royal Ave. Remove and replace storm main and add CB's and Manholes.
Static "ROAD CLOSED" signs with the dates, times and company contact must be put up and a letter to impact
Permit number: RUP2025-0030
LONG ST to GLENWOOD AVE
January 15, 2025 (All day) to February 19, 2025 (All day)
Full Road Closure, Local Traffic Only, Detour
Rutland Rd N 169 - one lane and sidewalk closure for material laydown and deliveries/hoisting. A pedestrian provision has been accounted for. Total of 165 sqm of workk zone.
Permit number: RUP2024-0180
Phone: 403-367-1330
Email: [email protected]
HWY 33 W to SHEPHERD RD
March 1, 2024 (All day) to September 30, 2025 (All day)
Lane Drop - Multi Lane Road
Saucier Ave 812 - closure of sidewalk, shoulder and single westbound lane of Saucier Ave. Site hoarding for 2025
Permit number: RUP2025-0064
Project contact: Brodie Scott
Email: [email protected]
RICHTER ST to ETHEL ST
January 1, 2025 (All day) to December 31, 2025 (All day)
Lane Drop - Multi Lane Road, No Disruption
Seasonal Permit 2025 - all non excavation work on various City streets
Permit number: RUP2025-0019
COLLISON RD to SIMPSON AVE
January 29, 2025 -
9:00am to 3:30pm
Single Lane Alternating
Sonora Dr 1708 - For rogers Cable - Digging up existing conduit in the utility right of way and repairing. Across the street from Sonora Dr 1708 (Sonora Dr 1709). This work is to repair a conduit to bring rogers cable to Sonora Dr 1708.
Permit number: RUP2025-0054
Project contact: Jim Drew
Email: [email protected]
CALDOW ST to BROADVIEW AVE
January 23, 2025 - 9:00am to January 24, 2025 - 4:00pm
Lane Drop - Multi Lane Road
Springfield Rd 2189 - manhole access for underground splicing and placing.
Traffic disruptions allowed 9am - 3:30 pm.
Permit number: RUP2025-0039
COOPER RD to BENVOULIN CT
January 27, 2025 - 9:00am to January 28, 2025 - 4:00pm
Lane Drop - Multi Lane Road
Springfield Rd @ Benvoulin Crt - Replace power pole for Allteck. Waiting for sidewalk repair to be done.
Permit number: RUP2024-1162
Project contact: Reid Bicknell
Email: [email protected]
COOPER RD to BENVOULIN CT
December 20, 2024 - 9:00am to January 25, 2025 - 5:00pm
Lane Drop - Multi Lane Road
BENVOULIN CT to BENVOULIN RD
December 20, 2024 - 9:00am to January 25, 2025 - 5:00pm
Lane Drop - Multi Lane Road
Springfield Rd/Belgo Rd/Willits Rd - Geotechnical boreholes. Holes are off road shoulder but will require the backhoe to be in the shoulder. Requesting permission to start the test pits on Belgo Rd at 8 am. Lane shifting proposed.
Permit number: RUP2025-0074
Project contact: Aiden Castillo
Email: [email protected]
SPRINGFIELD RD to CLARISSA RD
January 23, 2025 - 8:00am to January 24, 2025 - 3:30pm
Single Lane Alternating
BELGO RD to WILLITS RD
January 23, 2025 - 9:00am to January 24, 2025 - 3:30pm
Single Lane Alternating
SPRINGFIELD RD to SEAFORD RD
January 23, 2025 - 9:00am to January 24, 2025 - 3:30pm
Single Lane Alternating
SEAFORD RD to EASTBOURNE RD
January 23, 2025 - 9:00am to January 24, 2025 - 3:30pm
Single Lane Alternating
RUTLAND RD S to BELGO RD
January 23, 2025 - 9:00am to January 24, 2025 - 3:30pm
Single Lane Alternating
St Paul St 1499 - sidewalk closure to accommodate a man lift and welding truck to install HSS support beams on levels 2, 3 and 4. Install of the actual exterior projecting sign will follow within a couple of months. The signage company will survey the i
Permit number: RUP2025-0070
Project contact: Danilo Mueller
Email: [email protected]
BERNARD AVE to DOYLE AVE
January 20, 2025 - 7:00am to January 24, 2025 - 4:00pm
No Disruption
Sutherland Ave 1276/Pridham Ave 1255 - sidewalk closure across entire frontage and sidewalk closure on Pridham and portion of curb lane.
Permit number: RUP2025-0080
CAPRI ST to PACIFIC CT
January 1, 2025 (All day) to December 31, 2025 (All day)
No Disruption
WEST END OF ROAD to DEVONSHIRE AVE
January 1, 2025 (All day) to December 31, 2025 (All day)
No Disruption
Sutherland Ave 534 (back Lan e) - replacing vault in alleyway behind 534 Sutherland Ave. TMP attached. This was a City request. The current vault has eroded and makes noise when driven over as it is uneven. 3 to 4 hours approx.
Permit number: RUP2025-0010
DEAD END to ROWCLIFFE AVE
January 21, 2025 - 9:00am to January 22, 2025 - 4:30pm
Local Traffic Only, No Through Traffic, Detour
Trench Pl 751 - For Rogers Cable - Digging and repairing conduit in the utility right of way. The dig and repair location is beside the PED in front of Walrod St 731. This work will be approximately 3 hours.
Permit number: RUP2025-0055
Project contact: Jim Drew
Email: [email protected]
OXFORD AVE to TRENCH PL
January 23, 2025 - 9:00am to January 24, 2025 - 4:00pm
Lane Drop - Multi Lane Road
WALROD ST to JONES ST
January 23, 2025 - 9:00am to January 24, 2025 - 4:00pm
Lane Drop - Multi Lane Road
OKANAGAN BLVD to WALROD ST
January 23, 2025 - 9:00am to January 24, 2025 - 4:00pm
Lane Drop - Multi Lane Road
Underhill St & Baron Rd - closure of the sidewalk and bike lane on Baron Rd to accommodate construction. cyclists and peds will have signed detour route.
Crosswalk to be setup on Underhill.
Permit number: RUP2024-1159
Project contact: Esther Elechi
Email: [email protected]
DILWORTH DR to UNDERHILL ST
January 20, 2025 (All day) to December 31, 2025 (All day)
No Disruption
HAYNES RD to BARON RD
January 20, 2025 (All day) to December 31, 2025 (All day)
No Disruption
Union Road between Upper Canyon Dr and Begbie Rd - Upgrading of existing storm main for future developments. Extend Sanitary, water, and shallow utilities into future developments. Widen out road for new turning movements, and Multi Use Path. Concrete fla
Permit number: RUP2025-0077
BEGBIE RD to UPPER CANYON DR N
January 27, 2025 (All day) to May 15, 2025 (All day)
Local Traffic Only
Water Service Repairs - Annual Permit various City streets
Permit number: RUP2025-0016
FLINTOFT AVE to GUY ST
January 21, 2025 - 7:30am to January 22, 2025 - 3:00pm
Single Lane Alternating
TRONSON DR to NORTH END OF ROAD
January 21, 2025 - 10:00am to January 22, 2025 - 3:00pm
No Disruption
SPALL RD to BREDIN RD
January 21, 2025 - 7:30am to January 24, 2025 - 3:00pm
Single Lane Alternating
Water St 1580 & 1570 - Demolish building and construct new building. Hoarding required on Lawrence, lane and Water St
Permit number: RUP2024-0068
Project contact: Slava Korshunov
Email: [email protected]
LAWRENCE AVE to LANE
January 1, 2024 (All day) to February 28, 2025 (All day)
Lane Drop - Multi Lane Road
ABBOTT ST to WATER ST
January 1, 2024 (All day) to February 28, 2025 (All day)
Lane Drop - Multi Lane Road
Water St 1659 / Leon Ave - errect scafolding to close portion of walkway at the corner to work on building.
Permit number: RUP2024-0008
WATER ST to PANDOSY ST
January 5, 2024 (All day) to December 31, 2025 (All day)
No Disruption
HARVEY AVE to LEON AVE
January 5, 2024 (All day) to December 31, 2025 (All day)
No Disruption
Wyndham Rd 129 -
We are working for Fortis BC replacing two power poles and adding new conductors on Union Rd at Wyndham Cres, we will be digging in these new poles beside the existing ones, I have attached the Road Works Permit and the Notice to Procee
Permit number: RUP2025-0042
Project contact: Darren Belanger
Email: [email protected]
RITCHIE CT to UNION RD
January 15, 2025 - 8:00am to January 27, 2025 - 4:30pm
Single Lane Alternating